FOUNDRY
SOURCING COMPARISON

Lokset 23 × 900 into South Africa

Landed cost, lead time and stock for every plant that could make it — approved or not.

Deliver toPolandUnited StatesAustraliaSouth AfricaChileIndia25 000 cartridges a month · rolling 90-day average
✨ AURA · RECOMMENDATIONWitbank is both the cheapest and an approved route at €4.78 landed, 8 days ex-works. Source there and hold 6 667 cartridges of buffer to cover the lead time.
Recommended
Witbank
approved · €4.78 landed
Cheapest overall
€4.78
Witbank
Monthly demand
25 000 ea
South Africa
Cover on hand
12 d
9 860 ea at Witbank
Freight is AURA’s per-unit estimate from lane distance and the last 12 months of shipments; duty comes from the tariff table it maintains per entity. Verify both at quote.

7 possible sources · delivered to South Africa

PlantApproved to sellEx-worksFreightDutyLanded costMake + shipStock
Marl
Germany
Not approved€4.82€0.760.0%
€5.58
14 d
42 600
51 d of cover
Katowice
Poland
Not approved€4.19€0.770.0%
€4.96
15 d
66 400
80 d of cover
Newcastle
Australia
Not approved€5.41€0.8515.0%
€7.20
18 d
18 240
22 d of cover
Georgetown
United States
Not approved€5.98€1.0015.0%
€8.03
17 d
31 110
37 d of cover
Witbank
South Africa
Approved€4.55€0.230.0%
€4.78
8 d
9 860
12 d of cover
Jiangsu
China
Not approved€3.74€0.9415.0%
€5.38
24 d
120 300
144 d of cover
Santiago
Chile
Not approved€6.12€0.7115.0%
€7.86
23 d
2 140
3 d of cover
Landed cost = ex-works + freight + duty, per cartridge, in EUR. Make + ship adds the plant lead time to the lane transit estimate.